华星东方公司参建的江苏省无锡市惠联垃圾焚烧热电提标扩容项目烟气净化工程通过168小时试运行。
The flue gas cleaning (FGC) project, of which Huaxing East participated the construction, for Huilian Waste incineration plant expansion Wuxi, Jiangsu passed 168 hours of trial operation.
该项目建设2×850t/d 机械炉排炉,配2×18MW抽凝式汽轮机+2×20MW发电机组。烟气处理采用SNCR+SDA+干粉喷射+活性炭吸附+布袋除尘器+低温SCR,其中SDA系统为我司参与供货,并由我司提供工艺设计和性能保证,其保障了项目SO2、HCL的指标排放,为我司EP工程。
The project applied 2× 850 t/d mechanical grate furnace and 2×18 MW pumping turbine + 2×20MW generators. The FGC adopted SNCR + SDA + lime injection + activated carbon adsorption + bag house filter + low-temperature SCR, in which SDA system is supplied by Huaxing East. Huaxing East also provided process design and performance guarantee, which ensures the target emission of SO2 and HCL of the project. It is an EP project of Huaxing East.
华星东方在江苏省的业绩涵盖包括:无锡东部二期、张家港二期、徐州二期、上环投江北、淮安、淮北、盐城大丰、常州金坛、盐城响水、无锡益多等多个项目。
Huaxing East's achievements in Jiangsu province include: East Wuxi Phase II, Zhangjiagang Phase II, Xuzhou Phase II, Jiangbei for Shanghai Environment Investment, Huai‘an, Huaibei, Dafeng Yancheng, Jintan Changzhou, Xiangshui Yancheng, Wuxi for Yiduo and other projects.